Question 1
A contractor is currently considering whether to bid for a certain contract or not and, if the decision is to bid, which profit margin can be applied to increase the chance of winning the contract. It is estimated that preparing the bid will cost £3,000. The contractor estimates that there is a 50% chance that their bid will be put on the “short-list”, otherwise their bid will be rejected.
Hire a Professional Essay & Assignment Writer for completing your Academic Assessments
Native Singapore Writers Team
- 100% Plagiarism-Free Essay
- Highest Satisfaction Rate
- Free Revision
- On-Time Delivery
Once short-listed, the contractor will have to provide further detailed information that will cost £5,000. After that, their bid will be either accepted or rejected. The risk is that if the bid is unsuccessful, the contractor will lose the cost of preparing the bid. The contractor considers three possible bid prices that will give profits to £30,000, £35,000, and £40,000. The probability of these bids being accepted(if they are short-listed)is0.9,0.75, and 0.35 respectively.
- Draw a decision tree to represent this problem.
- What is the best option for the contractor? andWhy?
- Discuss how the contractor can increase his chance to win this contract.
Buy Custom Answer of This Assessment & Raise Your Grades
Singaporean students, navigating through Decision Analysis for Bidding on a Contract coursework? Let us ease your journey! Our assignment writing service in Singapore and Coursework Writing Help In Singapore are tailored to meet your needs. With our dedicated experts, achieving academic success is just a click away.
Looking for Plagiarism free Answers for your college/ university Assignments.
- HRM331: Talent Management – Strategic Shift from the War for Talent to the Wealth of Talent
- Marginalised Populations – The Structural and Cultural Exclusion of People Experiencing Homelessness in Singapore
- CVEN3501 Assignment 2: Groundwater Modelling of Drawdown from a Pumping Bore
- CSCI312 Assignment 2: Conceptual Modelling and Implementation of a Data Warehouse and Hive Queries
- CH2123 Assignnment : Fugacity, VLE Modeling & Henry’s Law Applications
- BAFI1045 Assignment -Constructing and Evaluating Passive and Active Portfolios Based on the Straits Times Index (STI)
- PSB501EN Assignment 1: Engineering Systems Integration: A Multi-Technique Approach to Mechanical Analysis
- FIN2210E/FIN2212E Group Assignment: Financial Risk Management Analysis of Bursa Malaysia Companies
- FLM101 Assignment: A Cinematic Dissection: Stylistic Elements and Their Thematic Significance
- Assignment: Transforming Talent in the AI Era: From War to Wealth through Ecosystem Innovation